1. ON 23 FEB. EMBOFFS MET GTE VP HERB EDGAR, MICHAEL BOGUSLAWSKI WHO REPRESENTS GTE IN AFRICA, AND LOCAL GTE PROJECT MANAGER. EDGAR SAID GTE HAD LOST LARGE AMOUNT OF MONEY IN CAMEROON AND THAT PURPOSE OF HIS VISIT WAS TO COLLECT DOLS 1 TO 1.5 MILLION (AMOUNT VARIED) WHICH HE CLAIMS GURC OWES OVER AND ABOVE CONTRACT PRICE. BASIS OF CLAIM IS THAT BECAUSE OF 2 YEAR BUREAUCRATIC DELAY ON PART OF GURC IN SIGNING CONTRACT GTE IS DOING WORK ON MICROWAVE PROJECT AT 1973 PRICES. EDGAR ACKNOWLEDGED THAT SOME OF MORE RECENT DELAYS ARE GTE'S FAULT BUT DISMISSED MOST GURC COMPLAINTS AS GROUNDLESS. HE STATED THAT GTE WILL FINISH CONTRACT BY END OF JUNE. ONCE GTE DEPARTS, HOWEVER, HE EXPECTS SYSTEM TO HAVE HIGH RATE OF DOWN TIME BECAUSE CAMEROONIANS ARE NOT CAPABLE OF MAINTAINING IT.
2. ON 24 FEB, AT REQUEST OF GURC, EMBOFF ATTENDED MEETING BETWEEN GTE AND PTT. MINISTER OF PTT PRESIDED. DURING MEETING IT QUICKLY BECAME CLEAR THAT IT WOULD BE FRUITLESS TO ATTEMPT TO UNRAVEL TECHNICALITIES OF ALLEGATIONS AND COUNTER ALLEGATIONS OF EACH SIDE. AT MINISTER'S REQUEST PTT AND GTE AGREED THAT TECHNICAL STAFFS WILL MEET AND WORK OUT EXACTLY WHAT NEEDS TO BE DONE IN ORDER TO WIND UP PROJECT BY END OF JUNE. ISSUE OF GTE CLAIM WAS RAISED BY EDGAR DURING MEETING BUT NOT DIRECTLY ADDRESSED BY GURC.
3. COMMENT. ONE DIFFICULTY CONFRONTING GTE IS THAT IT HAS NOT KEPT UP ITS CONTACTS IN CAMEROON. BOGUSLAWSKI IS RESPONSIBLE FOR CAMEROON, BUT BECAUSE OF PERSONAL PROBLEMS THIS WAS HIS FIRST VISIT IN THREE YEARS. AS A RESULT, GURC HAS ACCUMULATED A NUMBER OF FESTERING COMPLAINTS. GTE PLANS TO SEND BOGUSLAWSKI HERE MORE FREQUENTLY IN THE FUTURE AND OVER TIME HE BELIEVES THIS SHOULD IMPROVE SITUATION. OF COURSE, IF GTE HAS SOLD GURC A SYSTEM TOO COMPLEX FOR CAMEROONIANS TO MAINTAIN, (AS EDGAR AND PROJECT MANAGER BELIEVE) THEN BOTH GTE'S AND AMERICAN IMAGE IN GENERAL WILL SUFFER.
4. WITH REGARD TO MISSED APPOINTMENT, DJUOKU INSISTED THAT IT WAS SCHEDULED FOR 20 FEB. EDGAR AND PROJECT MANAGER SAID APPOINTMENT WAS SCHEDULED FOR 23 FEB. NEITHER THEY NOR WE UNDERSTAND CAUSE OF MIX-UP. SMYTHE
View original PDF
Document details
Source citation
U.S. Embassy, Yaoundé. “MAJOR PROJECT: GTE PERFORMANCE ON MICROWAVE CONTRACT.” March 3, 1979. 1979YAOUND01266_e.